WACC
Note: Highlighted cells in bold indicate the simulations of high and low values for the respective variable.
Table Table13 13
Detailed simulation table for India
Cost input | Current values | Low overnight cost | High overnight cost | Low IDC | High IDC | Low O&M cost | High O&M cost | Low inflation | High inflation | Low tax | High tax | Low WACC | High WACC |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Overnight cost | 3,125 | 3,125 | 3,125 | 3,125 | 3,125 | 3,125 | 3,125 | 3,125 | 3,125 | 3,125 | 3,125 | ||
IDC | 1,250 | 1,250 | 1,250 | 1,250 | 1,250 | 1,250 | 1,250 | 1,250 | 1,250 | 1,250 | 1,250 | ||
O&M cost | 91.45 | 91.45 | 91.45 | 91.45 | 91.45 | 91.45 | 91.45 | 91.45 | 91.45 | 91.45 | 91.45 | ||
Inflation | 6.0% | 6.0% | 6.0% | 6.0% | 6.0% | 6.0% | 6.0% | 6.0% | 6.0% | 6.0% | 6.0% | ||
Tax | 34.0% | 34.0% | 34.0% | 34.0% | 34.0% | 34.0% | 34.0% | 34.0% | 34.0% | 34.0% | 34.0% | ||
WACC | 7.94% | 7.94% | 7.94% | 7.94% | 7.94% | 7.94% | 7.94% | 7.94% | 7.94% | 7.94% | 7.94% | ||
Result | 5.36 | 5.05 | 5.59 | 4.40 | 5.70 | 5.18 | 5.53 | 8.78 | 3.05 | 5.17 | 6.01 | 3.43 | 7.46 |
Gour Gobinda Goswami: Formulating idea, writing, reviewing, investigation, and editing, validation, supervision.
Umama Rahman: Methodology, levelized cost estimation, model, original draft preparation.
Mehdi Chowdhury: Literature review, editing, draft preparation, organization of the paper.
This study is funded by North South University, Dhaka, Bangladesh, under its internal research grant for faculty members entitled “Conference, Travel, and Research Grant,” Cycle: 2019–20.
Declarations.
Not applicable.
The authors declare no competing interests.
1 We are grateful to an anonymous reviewer for suggesting us to add this section in the introductory part for sharpening the focus of the paper.
2 We are grateful to an anonymous reviewer for bringing up the issue of developing countries with high population density and low geographical space.
3 Unit 1 and 2 of Kudankulam are operating from 2013 and 2014, respectively.
4 The above two equations are modified from Singh et al. ( 2018 ) and Du and Parsons ( 2009 ).
5 The 90% depreciation rate and 10% salvage value are estimated following both Bangladesh Energy Regulatory Association ( 2016 ) and Singh et al. ( 2018 ). In contrast, the 10-year and 50-year schedule are following the depreciation schedule given in Bangladesh Energy Regulatory Association ( 2016 ).
• Bangladesh government is setting up two units of nuclear power plants in Rooppur with 1200 MW capacity each for the first time in its history.
• The total financial cost of this construction has already been estimated to be US$12.65 billion.
• This paper attempts to assess the broader economic cost of setting up this plant at Rooppur, Bangladesh, by using the discounted present value method developed by Du and Parsons ( 2009 ), MIT ( 2003 ; 2009 ; 2018 ), and Singh et al. ( 2018 ).
• The levelized cost of electricity (LCOE) has been estimated to be 9.36 cents/kWh, whereas the rate is 5.34 cents/kWh for a similar plant of Kudankulam Tamil Nadu, India.
• In terms of Bangladeshi currency, the LCOE is amounted to BDT 7.94/kWh. Hence, if the government can sell the electricity above this price, the project will be economically viable or profitable.
Publisher's Note
Springer Nature remains neutral with regard to jurisdictional claims in published maps and institutional affiliations.
Umama Rahman, Email: [email protected] .
Mehdi Chowdhury, Email: ku.ca.htuomenruob@yruhdwohcm .
Nuclear technology and applications.
You are here, iaea mission concludes site and external events design review for nuclear power plant in sri lanka.
If you would like to learn more about the IAEA’s work, sign up for our weekly updates containing our most important news, multimedia and more.
During an IAEA review mission in Sri Lanka, experts undertook geophysical studies at a potential site for a nuclear power plant in Pulmoddai, near the Trincomalee region. (Photo: J. Gunatilake, University of Peradeniya)
An International Atomic Energy Agency (IAEA) team of experts has concluded a seven-day safety review of Sri Lanka’s selection process to identify potential sites to build its first nuclear power plant. The South Asian country is pursuing the introduction of nuclear power to increase its low carbon power production to meet energy demand, tackle climate change and increase energy security.
The Site and External Events Design Review Service (SEED) mission, which took place from 30 May to 5 June, reviewed Sri Lanka’s adherence to IAEA guidance on site selection, including exclusion and screening criteria. Sri Lanka has completed the site survey stage and identified six candidate sites from three different regions. The next phase, which is ongoing, includes evaluation, comparison and ranking studies of the candidate sites.
The SEED mission was carried out at the request of the Government of Sri Lanka and hosted by the Sri Lanka Atomic Energy Board (SLAEB) under the purview of the Ministry of Power and Energy.
The team comprised of three experts from Canada, Pakistan and Türkiye, as well as one IAEA staff. They reviewed the site survey report, together with the siting process, siting criteria, data collection process and application of the management system for siting activities. The team also visited and observed one of the candidate sites in Pulmoddai, near the Trincomalee region.
“Sri Lanka is comprehensively screening site-specific external hazards in the site selection process, while following the IAEA safety standards and adopting best practices,” said mission team leader Ayhan Altinyollar, an IAEA Nuclear Safety Officer.
The team provided recommendations to optimize the site evaluation process to select the most favourable site. In particular, the IAEA team recommended that SLAEB:
As a good practice, the team noted that SLAEB has been conducting collaborative siting studies in an open and transparent manner with stakeholder organizations, such as the Geological Survey and Mines Bureau, Central Environmental Authority and the Department of Geology of University of Peradeniya.
“Sri Lanka has identified nuclear as a clean and green energy source to fulfil the future electricity demand in Sri Lanka. In March 2024, the Cabinet of Ministers made a strategic and knowledgeable commitment towards the country’s nuclear power planning programme. Interpretation and application of IAEA safety standards within the context of site selection for a nuclear power plant is crucial for a strong nuclear power programme in Sri Lanka,” said Professor Rexy Denzil Rosa, Chairman of SLAEB.
The mission team briefed the Secretary of the Ministry of Power and Energy, Sulakshana Jayawardhana, and the Director General of the Geological Survey and Mines Bureau, Ranjith Premasiri, about the review of Sri Lanka’s selection process and findings of the SEED mission.
Sri Lanka also hosted a national workshop on nuclear law in November 2023, as well as an IAEA Integrated Nuclear Infrastructure Review (INIR) mission in April 2022, which reviewed the country’s infrastructure development for a nuclear power programme.
The final SEED mission report will be delivered to the Government of Sri Lanka within three months.
About Site and External Events Design Review Service (SEED) missions
SEED missions are expert review missions that assist countries going through different stages in the development of a nuclear power programme. The service offers a choice of modules on which to focus the review, such as site selection, site assessment and design of structures, systems and components, taking into consideration site specific external and internal hazards.
In the case of site selection review, SEED missions assess the appropriate consideration of the safety issues in the site selection process.
Hosted by the Sri Lanka Atomic Energy Board (SLAEB) and under the purview of the Ministry of Power and Energy, the SEED mission was requested by the Government of Sri Lanka.
An International Atomic Energy Agency (IAEA) team of experts has concluded a seven-day safety review of Sri Lanka’s site selection process for its first nuclear power plant. The South Asian nation is aiming to adopt nuclear energy to enhance low carbon power production, address climate change, and bolster energy security.
The Site and External Events Design Review Service (SEED) mission, conducted from May 30 to June 5, evaluated Sri Lanka’s adherence to IAEA guidance on site selection, including exclusion and screening criteria. The country has identified six candidate sites from three regions following the completion of its site survey stage. The ongoing phase involves evaluation, comparison, and ranking of these sites.
The expert team, consisting of members from Canada, Pakistan, Türkiye, and an IAEA staff member, reviewed the site survey report, the siting process, criteria, data collection, and application of the management system for siting activities. They also visited and observed a candidate site in Pulmoddai, near the Trincomalee region.
“Sri Lanka is comprehensively screening site-specific external hazards in the site selection process, while following the IAEA safety standards and adopting best practices,” stated mission team leader Ayhan Altinyollar, an IAEA Nuclear Safety Officer.
The team provided recommendations to optimize the site evaluation process to select the most favorable site, including:
Further aligning the siting process with IAEA Safety Standard Series No. SSG-35, Site Survey and Site Selection for Nuclear Installations.
Collecting and incorporating additional site-specific information into the siting process.
The team also commended SLAEB for conducting collaborative siting studies in an open and transparent manner with stakeholder organizations such as the Geological Survey and Mines Bureau, Central Environmental Authority, and the Department of Geology of University of Peradeniya.
“Sri Lanka has identified nuclear as a clean and green energy source to fulfill future electricity demand. In March 2024, the Cabinet of Ministers committed to the country’s nuclear power planning programme. Interpretation and application of IAEA safety standards within the context of site selection is crucial for a strong nuclear power programme in Sri Lanka,” said Professor Rexy Denzil Rosa, Chairman of SLAEB.
The mission team briefed the Secretary of the Ministry of Power and Energy, Sulakshana Jayawardhana, and the Director General of the Geological Survey and Mines Bureau, Ranjith Premasiri, on their review of Sri Lanka’s selection process and the findings of the SEED mission.
Sri Lanka previously hosted a national workshop on nuclear law in November 2023 and an IAEA Integrated Nuclear Infrastructure Review (INIR) mission in April 2022, which assessed the country’s infrastructure development for a nuclear power programme.
The final SEED mission report will be delivered to the Government of Sri Lanka within three months.
About Site and External Events Design Review Service (SEED) missions
SEED missions are expert review missions that assist countries at various stages of developing a nuclear power programme.
The service offers modules focusing on siteselection, site assessment, and the design of structures, systems, and components, considering site-specific external and internal hazards. In the case of site selection review, SEED missions assess the safety considerations within the site selection process to ensure adherence to international standards and best practices.
Latest news, btech student's tragic fall in haryana: mystery surrounds suicide, south africa overcomes netherlands jinx in thrilling t20 world cup clash, speeding taxi collides with autorickshaw, injuring 12 including children, vincent aboubakar leads cameroon to victory amidst team turmoil.
Empowering healthcare facilities: safecare4covid’s role in epidemic preparedness in sub-saharan africa, addressing late antenatal care in cape town: a study on adolescent pregnancies, quantifying uncertainty in cybersecurity: the role of bayesian deep learning, future of agriculture: cutting-edge uav technology for automated fruit harvesting, connect us on.
Email: [email protected] Phone: +91-720-6444012, +91-7027739813, 14, 15
© Copyright 2024
We use cookies to provide the best experience for you. To find out more check our cookies and privacy policy
07 June 2024
Microreactor startup Radiant Industries has announced that the US Department of Energy has reviewed and approved the Safety Design Strategy for its Kaleidos microreactor in the National Reactor Innovation Center's Demonstration of Microreactor Experiments test bed at Idaho National Laboratory.
Past experience suggests the idea of energy transitions is not all it seems, argues Jean-Baptiste Fressoz. Plus the latest from JET, the USA's Russian uranium ban and China's small modular reactor project.
The Republic of Guinea and Rosatom have signed a memorandum of understanding to cooperate on the development of floating power units to supply electricity to the African country.
New Nuclear 07 June 2024
It is time for the USA to cash in on the experience of nuclear new-build at Vogtle, US Secretary of Energy Jennifer Granholm said at an event held to mark the completion of the two units in Georgia. Restarting recently retired nuclear plants could also play a part in meeting the need for new capacity.
Nuclear Policies 07 June 2024
WNN is a public information service of World Nuclear Association
International Atomic Energy Agency Director General Rafael Mariano Grossi says there "was an understanding" that Zaporizhzhia nuclear power plant's units "would not be restarted as long as nuclear safety and security remained in jeopardy due to the conflict".
Regulation & Safety 07 June 2024
The US Department of Energy has released a strategy aimed at accelerating the viability of commercial fusion energy in partnership with the private sector. The department also announced USD180 million to support fusion research at an event in Washington, DC.
Doe agrees partnerships for smr deployment, small is beautiful for federal funds, nuclear's flexibility is the 'magic' to create a clean energy future, polish ministry approves plans for rolls-royce smrs, facility to demonstrate rolls-royce smr module production, conference: nuclear growth relies on good policies, viewpoint: polina lion on rosatom's esg policies, edf completes ge steam power acquisition.
Australian attitudes towards energy sources have shifted markedly, the 20th edition of the Lowy Institute's annual poll has found, with six in ten now supportive of Australia using nuclear power to generate electricity.
Nuclear Policies 06 June 2024
Steady Energy said it is set to start construction of its first LDR-50 district heating reactor pilot plant in Finland next year, with potential sites including the Finnish capital Helsinki and two other cities.
New Nuclear 06 June 2024
The board of governors of the International Atomic Energy Agency has adopted a resolution calling on Iran to fully cooperate with the agency, including giving it access to locations and material for nuclear safeguards verification activities.
Members of Ukraine's parliament have backed a law approving the framework agreement between Ukraine and the European Bank for Reconstruction and Development for funding aimed at projects to boost safety measures at the Chernobyl nuclear power plant site and exclusion zone.
Regulation & Safety 06 June 2024
Memorandums of understanding covering education and training, infrastructure development and public opinion have been signed in the next stage of Burkina Faso and Russia's cooperation on peaceful uses of nuclear technology.
The Atlas railcar - developed by the US Department of Energy to transport used nuclear fuel and high-level radioactive waste - has been certified by the Association of American Railroads to operate on all major freight railroads in the USA.
Regulation & Safety 05 June 2024
The United States used to build nuclear-power plants affordably. To meet our climate goals, we’ll need to learn how to do it again.
Listen to this article
Produced by ElevenLabs and News Over Audio (NOA) using AI narration.
N uclear energy occupies a strange place in the American psyche—representing at once a dream of endless emissions-free power and a nightmare of catastrophic meltdowns and radioactive waste. The more prosaic downside is that new plants are extremely expensive: America’s most recent attempt to build a nuclear facility, in Georgia, was supposed to be completed in four years for $14 billion. Instead it took more than 10 years and had a final price tag of $35 billion — about 10 times the cost of a natural-gas plant with the same energy output.
But the United States might not have the luxury of treating nuclear energy as a lost cause: The Department of Energy estimates that the country must triple its nuclear-power output by 2050 to be on track for its climate targets. For all the recent progress in wind and solar energy, renewables on their own almost certainly won’t be enough. Arguably, then, we have no choice but to figure out how to build nuclear plants affordably again.
Half a century ago, nuclear energy seemed destined to become the power source of the future. The first commercial-reactor designs were approved in the 1950s, and by the late ’60s, America was pumping them out at a fraction of what they cost today. In 1970, the Atomic Energy Commission predicted that more than 1,000 reactors would be operating in the United States by the year 2000.
In the popular history of atomic energy in America, the turning point was the infamous meltdown at the Three Mile Island plant in 1979. In the aftermath of the accident, environmentalists pressured regulators to impose additional safety requirements on new and existing plants. Nuclear-energy advocates argue that these regulations were mostly unnecessary. All they did, in this telling, was make plants so expensive and slow to build that utility companies turned back to coal and gas. Activists and regulators had overreacted and killed America’s best shot at carbon-free energy.
This story contains some kernels of truth. The safety risk of nuclear energy is often wildly overblown. No one died at Three Mile Island, and later studies found that it didn’t have any adverse health effects on the local community. Even including the deadly meltdowns at Chernobyl and Fukushima, nuclear power has most likely caused only a few hundred deaths, putting its safety record on par with wind turbines and solar panels, which occasionally catch fire or cause workers to fall. (The immediate areas around the sites of the Chernobyl and Fukushima disasters have, however, been rendered uninhabitable for decades because of the potential dangers of radiation.) Nuclear waste can be harmful if mishandled, but isn’t difficult to store safely. Air pollution from fossil fuels, meanwhile, is estimated to kill anywhere from 5 million to 9 million people every year.
Read: Nuclear is hot, for the moment
The claim that excessive regulation single-handedly ruined the American nuclear industry, however, doesn’t hold up. The cost of building new nuclear plants was already rising before Three Mile Island. Several nuclear-energy experts told me that a major driver of those cost increases was actually a lack of industry standards. According to Jessica Lovering, the executive director of Good Energy Collective and a co-author of a widely cited study on the cost of nuclear energy, throughout the ’60s and ’70s, utilities kept trying to build bigger, more ambitious reactors for every new project instead of just sticking with a single model. (Lovering used to be the head of nuclear policy at the Breakthrough Institute—a think tank that tends to warn against excessive regulation.) “It’s like if Boeing went through all the trouble to build one 737, then immediately threw out the design and started again from scratch,” she told me. “That’s a recipe for high costs.” The 94 nuclear reactors operating in the United States today are based on more than 50 different designs. In countries such as France and South Korea, by contrast, public utilities coalesced around a handful of reactor types and subsequently saw costs remain steady or fall.
Lovering also noted that the overregulation story leaves out a crucial fact: Because of a slowing economy, electricity demand flatlined in the early 1980s, causing American utilities to stop building basically every electricity-generating resource, not just nuclear plants. By the time the U.S. finally did try to build them again, in 2013, the American nuclear industry had all but withered away. “In the 1970s, we had a whole ecosystem of unionized workers and contractors and developers and utilities who knew how to build this stuff,” Josh Freed, who leads the climate and energy program at Third Way, a center-left think tank, told me. “But when we stopped building, that ecosystem died off.” This became obvious during the disastrous Vogtle project, in Georgia—the one that ended up costing $35 billion. Expensive changes had to be made to the reactor design midway through construction. Parts arrived late. Workers made all kinds of rookie mistakes. In one case, an incorrect rebar installation triggered a seven-and-a-half-month regulatory delay. Experts estimate that by the time it was finished, the project was four to six times more expensive per unit of energy produced than plants built in the early ’70s.
Given the impracticality of nuclear energy, some environmentalists argue that we should focus on wind and solar. These technologies can’t power the entire grid today, because the sun doesn’t always shine and the wind doesn’t always blow. With enough advances in battery-storage technology , however, they could in theory provide 24/7 power at a far lower price than building nuclear plants. “The nuclear industry has been promising cheap, clean energy for decades at this point,” David Schlissel, a director at the Institute for Energy Economics and Financial Analysis, told me. “Why waste our money on false hopes when we could be putting it towards technologies that have a real chance of working?”
He may be right about the technology. But just because it might one day be technically feasible to power the entire grid with renewables doesn’t mean it will ever be politically feasible. That’s because wind and solar require land—a lot of land. According to Princeton University’s “Net-Zero America” study , reaching net-zero emissions with renewables alone would involve placing solar panels on land equivalent to the area of Virginia and setting up wind farms spanning an area equivalent to Arkansas, Iowa, Kansas, Missouri, Nebraska, and Oklahoma combined. The more land you need, the more you run into the meat grinder of American NIMBYism. Efforts to build renewables are already getting bogged down by local opposition , costly lawsuits , and permitting delays . These challenges will only intensify as the easiest sites come off the board.
Transmission lines, which are needed to transport renewable energy from where it’s generated to where it’s used, may present an even bigger challenge. Some lines have taken nearly two decades just to receive their full suite of approvals. “There’s a chance we will suddenly get our act together and overcome the many, many constraints to deploying renewables,” Jesse Jenkins, who leads the Princeton Zero-Carbon Energy Systems Research and Optimization Lab, told me. “But I’m certainly not willing to bet the fate of the planet on that happening.”
The case for nuclear , then, is less about technological possibilities than it is about political realities. Nuclear can generate the same amount of power while using 1/30th as much land as solar and about 1/200th as much as wind. Reactors can be built anywhere, not just in areas with lots of natural wind and sunshine, eliminating the need for huge transmission lines and making it easier to select sites without as much local opposition. And nuclear plants happen to generate the greatest number of high-paying jobs of any energy source, by far. (On average, they employ six times as many workers as an equivalent wind or solar project does and pay those workers 50 percent more.) That helps explain why four different towns in Wyoming recently fought over the right to host a nuclear project. Nuclear power is also the only energy source with overwhelming bipartisan support in Washington, which makes Congress more likely to address future bottlenecks and hurdles as they arise.
Brian Deese: The next front in the war against climate change
As for how to make the economics work, there are two schools of thought. One holds that if America forgot how to build nuclear because we stopped doing it, we just need to start back up. Pick a design, build lots of plants, and we’ll eventually get better. Other countries have done this with great success; South Korea, for instance, slashed the cost of constructing nuclear plants in half from 1971 to 2008. Here, the Vogtle project carries a silver lining: The second of the plant’s two reactors was about 30 percent cheaper to build than the first, because workers and project managers learned from their mistakes the first time around. “I consider Vogtle a success,” Mike Goff, acting assistant secretary for the Department of Energy’s Office of Nuclear Energy, told me. “We learned all kinds of hard lessons. Now we just need to apply them to future projects.”
The second school of thought is that we’ve been building nuclear reactors the wrong way all along. This camp points out that over the past half century, basically every kind of major infrastructure project—highways, skyscrapers, subways—has gotten more expensive, whereas manufactured goods—TVs, solar panels, electric-vehicle batteries—have gotten cheaper. Lowering costs turns out to be much easier when a product is mass-produced on an assembly line than when it has to be built from scratch in the real world every single time. That’s why dozens of companies are now racing to build nuclear reactors that are, in a phrase I heard from multiple sources, “more like airplanes and less like airports.” Some are simply smaller versions of the reactors the U.S. used to build; others involve brand-new designs that are less likely to melt down and therefore don’t require nearly as much big, expensive equipment to operate safely. What unites them is a belief that the secret to making nuclear cheap is making it smaller, less complicated, and easier to mass-produce.
Both paths remain unproven—so the Biden administration is placing bets on each of them. The president’s signature climate bill, the Inflation Reduction Act, included generous tax credits that could reduce the cost of a nuclear project by 30 to 50 percent, and the Bipartisan Infrastructure Law included $2.5 billion to fund the construction of two new reactors using original designs. The Department of Energy, meanwhile, is exploring different options for permanent nuclear-waste storage, investing in building a domestic supply chain for uranium, and helping companies navigate the process of getting reactor designs approved.
There’s no guarantee that the U.S. will ever relearn the art of building nuclear energy efficiently. Betting on the future of atomic power requires a leap of faith. But America may have to take that leap, because the alternative is so much worse. “We just have to be successful,” Mike Goff told me. “Failure is not an option.”
Support for this project was provided by the William and Flora Hewlett Foundation.
IMAGES
VIDEO
COMMENTS
Criteria and methods in nuclear power plants siting: a systematic literature review. ... Site selection for nuclear power plants (NPPs) is an important government policy that has received widespread public attention. This situation led researchers to develop several criteria for determining NPP location. Therefore, our study aims to summarize ...
Nuclear energy is presented as a real option in the face of the current problem of climate change and the need to reduce CO2 emissions. The nuclear reactor design with the greatest global impact throughout history and which has the most ambitious development plans is the Pressurized Water Reactor (PWR). Thus, a global review of such a reactor design is presented in this paper, utilizing the ...
A. The Alternatives The literature has identified three major alternative sitings 1) Land-based 2) Offshore 3) Underground. The proposed model will evaluate, in addition to the land-based siting, 13 different alternative sitings for nuclear power plants as shown in fig 1 & fig 2 in the literature section of this paper.
We draw the following conclusions: (1) This study reveals that over 133 countries or regions took part in research on nuclear power. The USA, Germany and Japan are the top three countries contributing to nuclear power literature, sharing 24.34%, 11.04% and 10.87% of papers, respectively.
Nuclear energy is a major part of power generation mix of many countries in the world. More than 430 nuclear power plants (NPPs) are operating and spreading all over the inhabited land. Although there were only a few NPPs accidents, social and environmental impacts were too high. These impacts have made the nuclear power safety a controversial issue. In order to enhance NPPs safety, one ...
Request PDF | Nuclear power plants alternative sitings: A literature review and research gaps | Nuclear energy is a major part of power generation mix of many countries in the world. More than 430 ...
Abstract. Nuclear power plants play a significant role in glo bal electricity generation, offering a reliable a nd low -carbon energy. source. Maximizing the efficiency of nuclear power plants is ...
DOI: 10.1080/23311886.2024.2354976 Corpus ID: 270236497; Criteria and methods in nuclear power plants siting: a systematic literature review @article{Susiati2024CriteriaAM, title={Criteria and methods in nuclear power plants siting: a systematic literature review}, author={Heni Susiati and Millary Agung Widiawaty and Moh.
In particular, a systematic review of decommissioning strategies, such as DD, ID, and ET, and the influencing factors associated with each strategy is needed from the researcher's point of view. In this regard, this study reviews the research literature on decommissioning strategies for nuclear power plants with a sustainable perspective.
In this regard, this study reviews the research literature on decommissioning strategies for nuclear power plants with a sustainable perspective. A systematic method involving a meta-analysis is used.
Given the information derived in the cross-country analysis this section provides a first review on resulting insights and identified knowledge gaps as well as a critical reflection on the limitations of the study. ... Sustainable decommissioning strategies for nuclear power plants: a systematic literature review. Sustainability, 14 (10) (May ...
Nuclear power can solve the energy trilemma of supplying baseload, clean and affordable power. However, a review of nuclear power plant (NPP) builds show mixed results, with delays in Finland and in the US offset by successes in China, South Korea and the UAE. In the West, financing for new builds has been difficult in the face of a deregulated ...
In particular, a systematic review of decommissioning strategies, such as DD, ID, and ET, and the influencing factors associated with each strategy is needed from the researcher's point of view. In this regard, this study reviews the research literature on decom-missioning strategies for nuclear power plants with a sustainable perspective.
The decommissioning of nuclear power plants (NPPs) is rapidly increasing because NPPs are not only no longer profitable in many cases but are also being decommissioned due to a lack of public acceptance or political reasons in many countries, particularly in Europe, following the explosion of the Fukushima Daiichi NPP. Accordingly, a significant body of research has focused on achieving safe ...
neighboring areas. Methods: This is a rapid review of the literature. We searched PUBMED and Medline for original studies of all large nuclear power plant disaster information documented in literature. Results: Eighty-three publications were identified in the review. The results are summarized in categories based on direct health effects such as immediate health effects, indirect health ...
Since PWRs are the most common nuclear power reactors, the breakdown of carbon emissions among the front end, construction and operation of NPPs and back end of the nuclear fuel cycle was analyzed (Figure 2; Supplementary Materials).The average carbon emissions at the front end, construction and operation and the back end were 11.45, 7.82 and 3.07 g CO 2 /kWh, respectively.
general pathways by which a nuclear power plant accident could cause economic costs (UNDP, UNICEF, UN-OCHA, & WHO, 2002). The figure, which is specific to Chernobyl, is also general in ... the present review. Building upon that report, we have undertaken a comprehensive literature review to identify information on the costs of the Chernobyl ...
As digital instrumentation in Nuclear Power Plants (NPPs) is becoming increasingly complex, both attack vectors and defensive strategies are evolving based on new technologies and vulnerabilities. Continued efforts have been made to develop a variety of measures for the cyber defense of these infrastructures, which often consist in adapting security measures previously developed for other ...
Literature review. Historically, nuclear power is not cost-competitive compared to fossil-fuel electricity or renewable electricity. Therefore, until today, the cost is a critical concern in the expansion of nuclear power. ... Besides different cost estimation methods, literature focusing on nuclear power plants in developing countries is very ...
Abstract. The paper provides a general overview of the nuclear power plant construction process with literature references to a more detailed treatment. The paper deals specifically with: (1) the planning process; (2) regulation and licensing (3) design and standarization; (4) project control; (5) organizational alternatives; and (6) time and ...
Many involve elaborate numerical weighting and ranking of alternatives, and some are computer-assisted. brief review of siting methodologies prepared by the Mitre Corporation for the U.S. Geological Survey, Methodologies for Power Plant Siting, 8. provides a useful, nontechnical overview of this process for the layman.
This review presents the recent advances in the field of nuclear power and addresses the aspects of nuclear economics, safety, nuclear design, spent fuel processing and waste management. 2. Nuclear economics. Nuclear power stations are hugely expensive to build but very cheap to run, yet the economics of nuclear power still look uncertain.
Sri Lanka also hosted a national workshop on nuclear law in November 2023, as well as an IAEA Integrated Nuclear Infrastructure Review (INIR) mission in April 2022, which reviewed the country's infrastructure development for a nuclear power programme. The final SEED mission report will be delivered to the Government of Sri Lanka within three ...
An International Atomic Energy Agency (IAEA) team of experts has concluded a seven-day safety review of Sri Lanka's site selection process for its first nuclear power plant. The South Asian nation is aiming to adopt nuclear energy to enhance low carbon power production, address climate change, and bolster energy security.
US microreactor clears initial stage of pre-testing safety review. New Nuclear. 07 June 2024. Microreactor startup Radiant Industries has announced that the US Department of Energy has reviewed and approved the Safety Design Strategy for its Kaleidos microreactor in the National Reactor Innovation Center's Demonstration of Microreactor ...
Produced by ElevenLabs and News Over Audio (NOA) using AI narration. Nuclear energy occupies a strange place in the American psyche—representing at once a dream of endless emissions-free power ...
The power crunch in California recently forced a rethinking of long-standing plans to shut down the Diablo Canyon nuclear plant on the Central Coast, long a hotbed of anti-nuclear protest. The ...
The U.S. Energy Information Administration publishes data on electricity generation from utility-scale and small-scale systems. Utility-scale systems include power plants that have at least 1 megawatt (MW) of electric generation capacity. Small-scale systems have less than 1 MW (1,000 kilowatts) of electric generation capacity.
Nuclear power plant (NPP) is a renewable energy that is currently considered one of the most reliable power sources [1, 2]. ... and even private sectors particularly for investigating the reopening of the decommissioned and inactive nuclear power plants worldwide. 2. Literature review and conceptual framework.
The Ghana Nuclear Power Programme Organisation was established in 2012 to oversee the preparation of the roadmap and implement activities for the inclusion of nuclear energy into the energy mix.