• Work & Careers
  • Life & Arts

Case study: Boeing’s Dreamliner

  • Case study: Boeing’s Dreamliner on x (opens in a new window)
  • Case study: Boeing’s Dreamliner on facebook (opens in a new window)
  • Case study: Boeing’s Dreamliner on linkedin (opens in a new window)
  • Case study: Boeing’s Dreamliner on whatsapp (opens in a new window)

By Ravi Anupindi

Roula Khalaf, Editor of the FT, selects her favourite stories in this weekly newsletter.

The story: When Boeing delivered its new Dreamliner 787 to All Nippon Airlines last month, it was the culmination of a long and drawn-out process. The first delivery came more than three years after the revolutionary aircraft – its innovation coming both from its use of composite materials and in terms of how the supply chain was managed – was first scheduled.

The challenge: One reason for the delay was an industry-wide shortage of aerospace fasteners, the nuts, bolts, rivets and washers that hold aircraft together. Although fasteners comprise only about 3 per cent of the cost of an aircraft, they became a serious supply-chain issue.

The worldwide downturn in the aircraft industry caused by the terrorist attacks of September 11 2001 led to consolidation among fastener makers, along with reduced capacity and smaller workforces. Although demand began to increase again, the fastener makers resisted adding capacity because of the continuing uncertainty over just how much demand there would be. So by the end of 2006 the fastener sector was running at only 80-90 per cent capacity.

The problem: In 2007 Boeing’s analysis of the shortage confirmed that there were fundamental ordering and scheduling problems. Because fasteners are used by Boeing as well as its partners, and each had its own way of procuring them, the fastener makers were unable to get a clear picture of demand. Above all, the process was not geared to forecasting demand.

Boeing’s study also revealed that the shortages might continue into 2012, even if fastener makers had increased capacity.

The response: Boeing decided to implement a programme that would change the fastener sector.

The most important changes would be better signalling of demand and the aggregation of supply-chain management in one place for Boeing and its six main production partners.

The new system, which Boeing named the Fastener Procurement Model (FPM), would use a central purchasing system to manage orders and inventory. It would also enable Boeing to negotiate a price directly with fastener makers to ensure more favourable pricing, both for itself and its partners. This was seen as key to encouraging the latter to implement the FPM.

In addition, Boeing and its production partners would make daily updates on inventory levels in a central web portal, which would help stabilise the supply chain.

The fastener makers would be responsible for replenishing inventory between set minimum and maximum levels. Boeing would also develop a forecasting algorithm to help smooth demand.

What happened: Challenges in rolling out the FPM quickly emerged.

Boeing’s main partners were worried that they would not benefit financially.

To deal with this, Boeing sent a formal request to the fastener makers asking for preliminary pricing data. But many manufacturers were both unhappy at sharing information on pricing and confused by the amount of information requested.

Moreover, Boeing had overlooked how important distributors were to the supply chain. The aircraft maker realised it had to consider more partners when planning FPM.

Boeing also met internal obstacles. It found that middle managers were sceptical of the claimed benefits and were worried about unintended consequences.

Key lessons: A lack of attention to commodity items such as fasteners can put a company at risk.

At Boeing, the effort to ensure fastener availability turned into something completely different as more parties than expected had to be extensively consulted and reassured. So, when planning and implementing a radical new procurement model – or any similar programme – it is vital to factor in all partners involved.

Ravi Anupindi is the Michael R. and Mary Kay Hallman Fellow and program director of the master of supply chain management course at the Ross School of Business, University of Michigan. To access the full case study, click here

Promoted Content

Follow the topics in this article.

  • Work & Careers Add to myFT
  • Terrorism Add to myFT
  • Boeing Co Add to myFT
  • Financial Times Add to myFT

Comments have not been enabled for this article.

International Edition

Case 39: Boeing 787 Dreamliner Project

  • First Online: 04 May 2022

Cite this chapter

boeing 787 dreamliner case study summary

  • B Rajesh Kumar 2  

Part of the book series: Management for Professionals ((MANAGPROF))

2186 Accesses

During Jan 2003, Boeing decided to go ahead with a development designation to develop a new super-efficient midsized airplane—the Boeing 787 with the focus on efficiency, economics, environmental performance, comfort and convenience along with e-enabled systems. The Boeing 787 was developed as a 200–250 seat airplane to provide nonstop, point to point service. The project though was expected to deliver the new airplane to customers by 2004 got delayed and the new planes entered into service by the year 2009. The 787 became the fastest selling wide body airplane in history. On Dec 15 2009, the 787 Dreamliner made its first flight from Paine Field in Everett, Washington. The 787-8 Dreamliner can accommodate 210–250 passengers on routes of 7650–8200 nautical miles while the 787-9 Dreamliner can carry passengers in the range of 250–290 on routes of 8000–8500 nautical miles. During the Paris Air Show held on June 18, 2013, Boeing launched the third member of the 787 family—787-10 Dreamliner. This series had orders for 102 airplanes from five customers. This longest aircraft of the 787 family achieved firm configuration in April 2014 and was scheduled for delivery in the year 2018. The new 787-10 has seating capacity in the range of 300–330 passengers and was designed to fly up to 7000 nautical miles. The new 787-10 aircraft covered more than 90% of the world’s twin aisle routes. The engines for the 787 aircrafts were provided by General Electric and Rolls Royce. The 787 is a groundbreaker in design, build and technology. It is the first airplane in which the composite materials form approximately 50% of the primary structure. The 787 Dreamliner can achieve 20–25% greater fuel efficiency and lesser carbon emissions.

This is a preview of subscription content, log in via an institution to check access.

Access this chapter

  • Available as EPUB and PDF
  • Read on any device
  • Instant download
  • Own it forever
  • Compact, lightweight edition
  • Dispatched in 3 to 5 business days
  • Free shipping worldwide - see info
  • Durable hardcover edition

Tax calculation will be finalised at checkout

Purchases are for personal use only

Institutional subscriptions

Further Reading

Justin Hayward, https://simpleflying.com/how-its-made-the-787/

https://www.boeing.com/history/products/787.page

https://www.boeing.com/features/2019/12/787-1st-flight-anniversary-12-19.page

http://www.inceptone.com/posts/projects/aerospace/boeing-787#overview

https://www.forbes.com/sites/stevedenning/2013/01/21/what-went-wrong-at-boeing/?sh=1cc61867b1b7

https://www.researchgate.net/publication/329241950_Crisis_in_Boeing_787_Dreamliner_An_Investigation_from_Project_Management_Control_Perspective

Gates, Dominic (September 24, 2011). “ Boeing celebrates 787 delivery as program’s costs top $32 billion” . The Seattle Times.

The eye of the storm . The Economist. May 14, 2016. ISSN 0013-0613 .

Jonathan R. Laing (April 27, 2013). “ Will Boeing’s Battery Fix Fly?” . Barron’s .

Download references

Author information

Authors and affiliations.

Dubai International Academic City, Institute of Management Technology, Dubai, United Arab Emirates

B Rajesh Kumar

You can also search for this author in PubMed   Google Scholar

Rights and permissions

Reprints and permissions

Copyright information

© 2022 The Author(s), under exclusive license to Springer Nature Switzerland AG

About this chapter

Kumar, B.R. (2022). Case 39: Boeing 787 Dreamliner Project. In: Project Finance. Management for Professionals. Springer, Cham. https://doi.org/10.1007/978-3-030-96725-3_43

Download citation

DOI : https://doi.org/10.1007/978-3-030-96725-3_43

Published : 04 May 2022

Publisher Name : Springer, Cham

Print ISBN : 978-3-030-96724-6

Online ISBN : 978-3-030-96725-3

eBook Packages : Economics and Finance Economics and Finance (R0)

Share this chapter

Anyone you share the following link with will be able to read this content:

Sorry, a shareable link is not currently available for this article.

Provided by the Springer Nature SharedIt content-sharing initiative

  • Publish with us

Policies and ethics

  • Find a journal
  • Track your research

Brought to you by:

Harvard Business School

Boeing 787: The Dreamliner

By: Richard L. Nolan, Suresh Kotha

Boeing dominated the commercial airline manufacturing business since bringing out the first commercial airline jet airliner. But in 2005, it delivered fewer new planes than its fast-moving…

  • Length: 18 page(s)
  • Publication Date: Apr 22, 2005
  • Discipline: Operations Management
  • Product #: 305101-PDF-ENG

What's included:

  • Teaching Note
  • Educator Copy
  • Supplements

$4.95 per student

degree granting course

$8.95 per student

non-degree granting course

Get access to this material, plus much more with a free Educator Account:

  • Access to world-famous HBS cases
  • Up to 60% off materials for your students
  • Resources for teaching online
  • Tips and reviews from other Educators

Already registered? Sign in

  • Student Registration
  • Non-Academic Registration
  • Included Materials

Boeing dominated the commercial airline manufacturing business since bringing out the first commercial airline jet airliner. But in 2005, it delivered fewer new planes than its fast-moving competitor, Airbus. Boeing responded by transforming its manufacturing business and introducing the first "all-composite" commercial airplane: the 787 (the Dreamliner). In addition to being a revolutionary new commercial airliner, the 787 attempts to change the large "spoke-and-hubs" airport operation to nonstop travel between many new "city-pairs" worldwide.

Learning Objectives

To understand contemporary competitive strategy, required business transformation, and dynamic risk management.

Apr 22, 2005 (Revised: Jun 21, 2005)

Discipline:

Operations Management

Geographies:

United States

Industries:

Aerospace sector

Harvard Business School

305101-PDF-ENG

We use cookies to understand how you use our site and to improve your experience, including personalizing content. Learn More . By continuing to use our site, you accept our use of cookies and revised Privacy Policy .

boeing 787 dreamliner case study summary

PDXScholar logo with slogan Access for All.

Home > School, College, or Department > MCECS > ETM > ETM Student Projects > 818

Engineering and Technology Management Student Projects

Boeing dreamliner:a project management study.

Fahad Aldhaban , Portland State University Chris McGinnis , Portland State University Wendy Peterman , Portland State University Noah Third , Portland State University Tom Torres , Portland State University

Document Type

Publication date.

Tim Anderson

Course Title

Project Management

Course Number

The 787 Dreamliner aircraft project required not only the application and integration of new construction materials, it also required new project management techniques for Boeing. By outsourcing most of the aircraft fabrication, Boeing’s primary role changed from designer and manufacturer to system integrator. Hindsight shows that more preparation and planning was needed for this transition. This case study review of the Boeing Dreamliner examines the project management techniques actually employed during the initiation and execution phases of the project. Techniques evolved from the start of the project to what is used currently. Best practices and recommendations for how a large-scale outsourced project could be managed are described. During the initiation phase, Boeing decided to outsource both design and manufacturing. Outsourcing core competencies is a risk to the main contractor’s design and manufacturing edge. The authors recommend selecting those subcontractors with a five step plan, based on selection criteria and culminating with clearly defined expectations. Boeing’s selection was strongly based on cost and market access, and the subcontractor understanding of work expectations initially differed from Boeing’s. It is important to work closely with subcontractors when advanced technology and key components are at stake. Boeing is doing this now, more effectively than at the start. Regular monitoring and control has improved as the project has progressed. Finally, delays and issues show after the fact that Boeing’s early work would have benefited from more robust risk management methods. Risk management techniques are discussed as are improvements Boeing has implemented currently.

In Copyright. URI: http://rightsstatements.org/vocab/InC/1.0/ This Item is protected by copyright and/or related rights. You are free to use this Item in any way that is permitted by the copyright and related rights legislation that applies to your use. For other uses you need to obtain permission from the rights-holder(s).

Persistent Identifier

http://archives.pdx.edu/ds/psu/22869

Citation Details

Aldhaban, Fahad; McGinnis, Chris; Peterman, Wendy; Third, Noah; and Torres, Tom, "Boeing Dreamliner:A Project Management Study" (2009). Engineering and Technology Management Student Projects . 818. http://archives.pdx.edu/ds/psu/22869

Since November 27, 2017

Included in

Technology and Innovation Commons

Advanced Search

  • Notify me via email or RSS
  • Featured Collections
  • All Authors
  • Schools & Colleges
  • Dissertations & Theses
  • PDXOpen Textbooks
  • Conferences
  • Collections
  • Disciplines
  • Faculty Expert Gallery
  • Submit Research
  • Faculty Profiles
  • Terms of Use
  • Feedback Form

Home | About | My Account | Accessibility Statement | Portland State University

Privacy Copyright

Boeing and the 787 Dreamliner

Ieee account.

  • Change Username/Password
  • Update Address

Purchase Details

  • Payment Options
  • Order History
  • View Purchased Documents

Profile Information

  • Communications Preferences
  • Profession and Education
  • Technical Interests
  • US & Canada: +1 800 678 4333
  • Worldwide: +1 732 981 0060
  • Contact & Support
  • About IEEE Xplore
  • Accessibility
  • Terms of Use
  • Nondiscrimination Policy
  • Privacy & Opting Out of Cookies

A not-for-profit organization, IEEE is the world's largest technical professional organization dedicated to advancing technology for the benefit of humanity. © Copyright 2024 IEEE - All rights reserved. Use of this web site signifies your agreement to the terms and conditions.

Boeing's revolutionary 787 Dreamliner has changed air travel forever. Here's how the company left competitors in the dust with a risky $8 billion bet.

  • First flown in 2009, the Boeing 787 was the first next-generation plane produced by a major aircraft manufacturer.
  • The jet was produced following the success of the Boeing 777, but it has faced setbacks over the years.
  • Quality concerns halted deliveries of the jet in 2020, but the FAA recently gave Boeing the green light to resume.

The Boeing 787 Dreamliner brought aviation into a new next-generation era when it took its first flight on December 15, 2009, and represented the future for Boeing Commercial Airplanes.

boeing 787 dreamliner case study summary

Source: Boeing

After years of building widebody aircraft with four engines, it wasn't until the 1990s that Boeing shifted to twin-engine dual-aisle aircraft.

boeing 787 dreamliner case study summary

Following the success of the 777, Boeing's best-selling wide-body planes, Boeing decided to continue the trend with a focus on efficiency and launched a new program in 2003 dubbed the "7E7."

boeing 787 dreamliner case study summary

The "E" would be the focal point for the aircraft, representing that the jet would lead in such factors as efficiency, economics, and environmental standards.

boeing 787 dreamliner case study summary

Instead of trying to level up the 777, Boeing looked back to see which seat market could be improved. It decided upon the 200-to-250-seat market that was served by the Boeing 767. The 7E7 wouldn't be Boeing's largest or fastest plane, but it didn't need to be.

boeing 787 dreamliner case study summary

The new aircraft would be called the Dreamliner following a worldwide vote and given the designation of the 787 as it followed the 777. Other potential names for the aircraft included the Global Cruiser, eLiner, and Stratoclimber.

boeing 787 dreamliner case study summary

Boeing began the $8 billion development of the aircraft in 2004 when Japan's All Nippon Airways placed a $6 billion order for 50 of the type, making Boeing history with the largest order for a new passenger jet aircraft.

boeing 787 dreamliner case study summary

Source: Boeing and New York Times

Before production on the first model began, Boeing was already touting its capabilities including ranges of up to 8,500 nautical miles, 20 percent less fuel consumption compared to similar aircraft and a slew of passenger-friendly amenities.

boeing 787 dreamliner case study summary

Airlines would have a choice with the Dreamliner on what would be powering the aircraft with Boeing installing a standard engine interface to accommodate two models, the General Electric GEnx…

boeing 787 dreamliner case study summary

...and the Rolls Royce Trent 1000, the engine which would later cause trouble for the aircraft.

boeing 787 dreamliner case study summary

Driving its efficiency would be its one-piece carbon fiber fuselage, a lightweight alternative to aluminum that reduced the need for rivets and panels to assemble the aircraft.

boeing 787 dreamliner case study summary

Source: New York Times

Analysts were watching its development closely as an aircraft of this caliber had never been attempted before and it was a big bet for Boeing that would determine its position in commercial aviation for years to come.

boeing 787 dreamliner case study summary

Though initial sales were record-breaking, Boeing would ultimately have to live up to its promises of increased efficiency and better economics on a new type of plane it had never built before.

boeing 787 dreamliner case study summary

Boeing would produce three variants, the smaller -8, the mid-size -9, and the larger -10.

boeing 787 dreamliner case study summary

Production would be a global affair, with companies in countries such as the United Kingdom, Japan, France, and Italy taking part in developing various aspects of the aircraft.

boeing 787 dreamliner case study summary

When the first -8 variant was first unveiled in 2007, the aircraft was unlike anything flying at the time and looked nothing like any other products that came from Boeing's facilities.

boeing 787 dreamliner case study summary

Everything about the aircraft's appearance was distinct including the cockpit windows…

boeing 787 dreamliner case study summary

...chevron on the back of the engines to reduce noise…

boeing 787 dreamliner case study summary

...and the wings.

boeing 787 dreamliner case study summary

The smaller -8 can seat up to 248 passengers in a two-class configuration and fly up to 7,305 nautical miles, almost the distance between New York and Bangkok.

boeing 787 dreamliner case study summary

On the inside, the Dreamliner promises a spacious cabin with lower cabin altitude pressure allowing higher onboard humidity levels...

boeing 787 dreamliner case study summary

...as well as larger windows with dimmers instead of shades...

boeing 787 dreamliner case study summary

...and an ultra-modern cockpit with high-definition displays.

boeing 787 dreamliner case study summary

By the time it debuted, the unique aircraft already had over $100 billion in orders for 677 models.

boeing 787 dreamliner case study summary

The new plane was all set to be delivered to All Nippon Airways in 2008 until Boeing ran into production problems. Issues with the aircraft's suppliers and primary engine manufacturer Rolls Royce had pushed back test flights and the first flight of the aircraft was pushed back until late 2009.

boeing 787 dreamliner case study summary

The aircraft finally flew for the first time on December 15, 2009, marking the start of the next-generation revolution in aviation and immediately rendering iconic aircraft like the Boeing 747 and Airbus A380 obsolete.

boeing 787 dreamliner case study summary

After a year and a half of test flights, the first Dreamliner was delivered to All Nippon Airways on September 26, 2011, nearly ten years following its order.

boeing 787 dreamliner case study summary

All Nippon Airways would be one of the Dreamliner's biggest fans, using all three variants to round out its fleet and shunning Airbus' rival offering, the A350 XWB.

boeing 787 dreamliner case study summary

After All Nippon took delivery of the first seven Dreamliners, deliveries to other customers began, including Japan Airlines...

boeing 787 dreamliner case study summary

Source: Planespotters.net

...Ethiopian Airlines…

boeing 787 dreamliner case study summary

...United Airlines…

boeing 787 dreamliner case study summary

...LOT Polish Airlines…

boeing 787 dreamliner case study summary

...Qatar Airways…

boeing 787 dreamliner case study summary

...British Airways…

boeing 787 dreamliner case study summary

...and Aeromexico.

boeing 787 dreamliner case study summary

Not long after the first delivery of the -8, Boeing debuted another newborn — the 787-9. The younger sibling first flew on September 17, 2013.

boeing 787 dreamliner case study summary

As the middle child of the family, the -9 was 20 feet longer than the -8, seating up to 296 passengers in a two-class configuration. It can also fly 250 nautical miles further than its older sibling.

boeing 787 dreamliner case study summary

This time, Air New Zealand took delivery of the first aircraft, which would become its flagship. The plane went on to fly some of Air New Zealand's longest routes, including between Auckland and Houston…

boeing 787 dreamliner case study summary

…and will fly what will be the fourth-longest route in the world between Auckland and New York starting in September.

boeing 787 dreamliner case study summary

Air New Zealand will operate the 4th longest flight in the world when it launches the first-ever nonstop route between the US East Coast and the South Pacific nation

Long, thin routes, such as the ones Air New Zealand would be using the plane, were precisely the type that Boeing promised it could fly. The Dreamliner allowed airlines to open up routes to previously unviable markets.

boeing 787 dreamliner case study summary

British Airways used the aircraft for a similar purpose, opening up routes from London to smaller markets in the US including Charleston, South Carolina; Nashville, Tennessee; New Orleans, and Pittsburgh.

boeing 787 dreamliner case study summary

Many of the operators of the -8 jumped onboard the -9 with orders from airlines such as All Nippon Airways…

boeing 787 dreamliner case study summary

...United Airlines,…

boeing 787 dreamliner case study summary

...and Japan Airlines.

boeing 787 dreamliner case study summary

But, the -9 saw many first-time customers purchasing the aircraft besides Air New Zealand, favoring the greater capacity and range, including Virgin Atlantic Airways…

boeing 787 dreamliner case study summary

...Etihad Airways…

boeing 787 dreamliner case study summary

...Air Canada…

boeing 787 dreamliner case study summary

...Vietnam Airlines…

boeing 787 dreamliner case study summary

...KLM Royal Dutch Airlines…

boeing 787 dreamliner case study summary

...Qantas...

boeing 787 dreamliner case study summary

...and LATAM Airlines.

boeing 787 dreamliner case study summary

The efficiency offered by the aircraft quickly allowed it to dominate the list of the world's longest flights and create new ones, including San Francisco to Singapore operated by a United Airlines Boeing 787-9, which is a 7,339-nautical mile route…

boeing 787 dreamliner case study summary

Source: Forbes

...and Perth to London operated by a Qantas 787-9 Dreamliner, a 7,829-nautical mile route that became the first nonstop link between Australia and the United Kingdom.

boeing 787 dreamliner case study summary

Qantas even used the aircraft to test nonstop flights from London and New York to Sydney, known as Project Sunshine.

boeing 787 dreamliner case study summary

Qantas will launch the world's longest flights, flying nonstop to New York and London from Sydney in 2025 — see what the 20-hour flights will look like

The longest-ever nonstop Boeing 787 flight was operated by Comlux in March 2021, flying 12,106 miles from Seoul, South Korea, to Buenos Aires, Argentina. The ultra-long-haul flight lasted 20 hours and 19 minutes.

boeing 787 dreamliner case study summary

Source: Aviacionline

While the Dreamliner is revolutionary in its efficiency and performance, the aircraft also sparked a low-cost revolution, with multiple budget long-haul carriers adopting the aircraft as a way to bring down operating costs.

boeing 787 dreamliner case study summary

Norwegian Air Shuttle's low-cost long-haul spinoff, aptly named Norwegian Long-Haul, used the aircraft to fly transatlantic routes between Europe and North America with advertised fares as low as $99 for a base ticket.

boeing 787 dreamliner case study summary

However, COVID-19, combined with other factors like increased competition, forced Norwegian to stop long-haul flying in 2021. The carrier said it will not resume the service post-pandemic.

boeing 787 dreamliner case study summary

Nevertheless, other budget carriers, including Singapore-based Scoot and Australia-based Jetstar, continue to fly the Dreamliner long-haul.

boeing 787 dreamliner case study summary

European low-cost startup Norse Atlantic Airlines also flies the Dreamliner, which it calls "Longships," across the Atlantic. The carrier started operations in June 2022 and hopes to fill the market gap left behind by Norwegian.

boeing 787 dreamliner case study summary

What passengers can expect when booking Europe's newest low-cost airline that will begin service to the US this summer

The final and largest Dreamliner variant, the 787-10, took the skies on March 31, 2017, eight years after the first variant did so in 2009.

boeing 787 dreamliner case study summary

The 787-10 is 18 feet longer than the -9 and 38 feet longer than the -8, and is able to seat 336 passengers in a two-class configuration.

boeing 787 dreamliner case study summary

However, the shorter-ranged aircraft is only able to fly as far as 6,330 nautical miles, which is about 975 nautical miles fewer than the -8, and 1,235 nautical miles shorter than the -9.

boeing 787 dreamliner case study summary

The first 787-10 was delivered to Singapore Airlines on March 25, 2018, and the full Dreamliner family was operating passenger flights all over the world soon after.

boeing 787 dreamliner case study summary

United Airlines became the first and only US operator of all three variants in 2018, with the airline being an early adopter of the 787-8 and subsequently taking delivery of each additional variant as they became available.

boeing 787 dreamliner case study summary

Despite its success, the 787 was not without its issues as the -8 fleet was grounded in 2013 following a series of malfunctions with the aircraft's battery.

boeing 787 dreamliner case study summary

The grounding only lasted four months, but permanently scarred the 787's entry into service after images like this one of an ANA 787 making an emergency landing circulated.

boeing 787 dreamliner case study summary

Source: FlightGlobal

Once that issue was resolved, another arose in the aircraft's Rolls Royce Trent 1000 engines, where parts of the engine were cracking.

boeing 787 dreamliner case study summary

Source: CNBC

The issue, which is ongoing, has cost Rolls Royce over $1 billion and grounded 787 fleets equipped with the manufacturer's engines, crippling numerous airlines and forcing them to spend millions on leased aircraft.

boeing 787 dreamliner case study summary

As of 2022, most of the Trent 1000 issues have been resolved, though Rolls-Royce said there is one modification that will be completed next year.

boeing 787 dreamliner case study summary

Source: Reuters

While Boeing hoped that would be the end of its 787 problems, another came up in 2019 when engineers voluntarily grounded eight planes due to paper-width gaps in the fuselage.

boeing 787 dreamliner case study summary

Source: Wall Street Journal

"Individually, these issues, while not up to specifications, still meet limit load conditions," Boeing said at the time. "When combined in the same location, however, they result in a condition that does not meet limit load requirements."

boeing 787 dreamliner case study summary

Shortly after, the Federal Aviation Administration launched its own investigation of the Dreamliner. In October 2020, future deliveries of the jet were paused, though Boeing was still able to deliver 14 jets by May 2021.

boeing 787 dreamliner case study summary

Source: Aviation International News

However, the FAA re-halted deliveries the same month over inspection method concerns, and Boeing was left with 120 jets, worth a collective $25 billion, sitting stagnant.

boeing 787 dreamliner case study summary

Source: WSJ

After 15 months of waiting, the FAA gave Boeing the green light to resume deliveries, with the first 787 going to American Airlines on Wednesday.

boeing 787 dreamliner case study summary

Source: American Airlines

The agency still says it will inspect all Dreamliner airworthiness ahead of future deliveries. According to the Wall Street Journal, American's plane was approved on Monday.

boeing 787 dreamliner case study summary

Source: Reuters , Wall Street Journal

FAA acting Administrator Billy Nolen met with inspectors at Boeing's South Carolina Delivery Center on August 4 ahead of the plane's final approval.

boeing 787 dreamliner case study summary

His visit was "to ensure that the FAA is satisfied that Boeing has taken the appropriate steps to improve manufacturing quality and to guarantee the autonomy of workers who ensure regulatory compliance on the company's assembly lines."

boeing 787 dreamliner case study summary

Despite its issues and initial unprofitability, the Dreamliner has grown to be one of Boeing's best-sellers with nearly 1,500 orders.

boeing 787 dreamliner case study summary

Once word of the Dreamliner and its next-generation capabilities was announced, rival manufacturer Airbus also jumped into the market and began developing the A350 XWB and the Airbus A330neo, the 787's main competitors.

boeing 787 dreamliner case study summary

Airbus recently delivered the 350th A350 plane, its answer to Boeing's revolutionary 787 Dreamliner. Here's how the new aircraft is reshaping air travel.

The Dreamliner was first in the market, however, and its legacy can be seen at every major airport with airlines all over the world on every populated continent adopting the type.

boeing 787 dreamliner case study summary

  • Main content

ICMR India

Search Case Studies

Case details, case categories.

Business Environment Business Ethics Business Reports Business Strategy Corporate Governance Economics Enterprise Risk Management Finance HRM Innovation Insurance IT and Systems Leadership & Entrepreneurship Marketing Miscellaneous Operations Project Management Sustainability Women Empowerment

Boeing 787 Dreamliner: Innovation Gone Wrong?

Case Details

The case is structured to achieve the following teaching objectives:

  • Understand the importance of innovation in the aerospace industry and how Boeing managed the supply chain to come up with a product that was hailed as a major innovation;
  • Discuss the reasons for the post launch problems faced by the 787 Dreamliner;
  • Analyze the pros and cons of outsourcing in aviation;
  • Discuss and debate whether the 787 Dreamliner can be considered an innovation in light of the problems it was facing.
  • Explore ways in which Boeing could salvage the situation.

Supply chain, Supply chain management, Outsourcing, Innovation, Operations management, Manufacturing, Design, Collaborative manufacturing, Value engineering, Strategy, Implementation

TheCaseSolutions.com

  • Order Status
  • Testimonials
  • What Makes Us Different

Boeing 787: The Dreamliner Harvard Case Solution & Analysis

Home >> Harvard Case Study Analysis Solutions >> Boeing 787: The Dreamliner

boeing 787 dreamliner case study summary

Boeing dominate commercial enterprises for the production of airlines, as revealing the first commercial airliner. But in 2005, she placed fewer new planes than its fast-moving rival, Airbus. Boeing responded by turning its manufacture and implementation of business first "all-composite" commercial aircraft: 787 (Dreamliner). In addition to the revolutionary new commercial airliner, the 787 attempts to change the large "spoke-and-center" Airport operation nonstop travel between many of the new "city pairs" around the world. "Hide by Richard L. Nolan, Suresh Kotha Source : Harvard Business School 18 pages. Publication Date: April 22, 2005. Prod. #: 305101-PDF-ENG

Related Case Solutions & Analyses:

boeing 787 dreamliner case study summary

Hire us for Originally Written Case Solution/ Analysis

Like us and get updates:.

Harvard Case Solutions

Search Case Solutions

  • Accounting Case Solutions
  • Auditing Case Studies
  • Business Case Studies
  • Economics Case Solutions
  • Finance Case Studies Analysis
  • Harvard Case Study Analysis Solutions
  • Human Resource Cases
  • Ivey Case Solutions
  • Management Case Studies
  • Marketing HBS Case Solutions
  • Operations Management Case Studies
  • Supply Chain Management Cases
  • Taxation Case Studies

More From Harvard Case Study Analysis Solutions

  • Balliss Benchmark A
  • Aristotle’s understanding of the nature of the human soul
  • Leadership Forum: Globalization Lessons from the C-Suite
  • Commitment to Share
  • IBMs Reinventing Education (A)
  • Project Financial Analysis
  • Scientific Glass Inc.: Inventory Management

Contact us:

boeing 787 dreamliner case study summary

Check Order Status

Service Guarantee

How Does it Work?

Why TheCaseSolutions.com?

boeing 787 dreamliner case study summary

Richard L. Nolan

More from the authors.

  • Faculty Research

Boeing Commercial Airplanes: Industry Leadership Lost (Four Key Decisions)

Performance hacking: the contagious business practice that corrodes corporate culture, undermines core values, and damages great companies, the creative consulting company.

  • Boeing Commercial Airplanes: Industry Leadership Lost (Four Key Decisions)  By: Richard L. Nolan and Robert D Austin
  • Performance Hacking: The Contagious Business Practice that Corrodes Corporate Culture, Undermines Core Values, and Damages Great Companies  By: Robert D. Austin and Richard L. Nolan
  • The Creative Consulting Company  By: Robert S. Kaplan, Richard Nolan and David P. Norton

Boeing 787 Dreamliner: Case Study

boeing 787 dreamliner case study summary

Show More Introduction Boeing 787 Dreamliner is the project plan of Boeing company about light weight aircraft with high technology. The project of this aircraft has facing several problems such as software problem that led to engine shutting down automatically, lithium ion battery that causes fire inside the aircraft and others problem that led delay in the production. The Boeing 787 has 3 different categories which are 787-3 that has been designed to fit in 250 passengers, 2 class, short range body and with range of 2,500 to 3,050 nautical miles (4,650 to 5,650 km) because the aircraft have les market therefore it only popular in Japanese market because it adapts to local customer’s demand, 787-8 with 242 passengers seat and can fly for 13,621 km. …show more content… The cost of delay has actually risk the project to cost for $12 billion. 1.2 Outsourcing Upon Outsourcing from the journal article of (Forbes, 2015) Boeing made several problems in their decision to outsource their aircraft plan. The purpose is to reduce the project plan time of Dreamliner from 6 years to 4 years and cost from $10 billion to $6 billion however, the project plan does not turn out to be exactly with the plan, Boeing suffer from delay of 3 more year ahead from it planned and thus led to over budget of billions dollars. First, Boeing trying to improve the substantiality of flying experience by using the material of aluminium, carbon and titanium that could allow to increase humidity and cabin pressure to be maintain in passenger cabin. The material help to reduce weight in the aircraft body ad thus enable 787 to fly whenever it likes …show more content… The data loader backings the insertion of data of operational software into the appropriate avionics systems. Boeing 787 also use digital fly-by-wire system that function for flight control computers and the actuator control electronics, plus sensors to support the fly-by-wire computations. It also deliveries the mode control panels the pilot typically uses when the autopilot function is affected, as well as some batteries for backup power. The flight control electronic package includes cabinets containing computer modules and actuator control electronics modules that effectively drive the actuators, along with power conditioning modules. 1.4 Supply Chain Boeing using just-in-time ordering, point-of-use delivery and internal kitting to streamline the product process for the uses of suppliers. The supply chain tool that Boeing uses is consumption based ordering it allows suppliers to use Boeing inventory levels with suppliers and the suppliers can use the system only when Boeing inventory levels drop under definite edges. The value chain lets suppliers to react based on their needs and to adapt to demand of the aircraft rather than wanting the order of the Boeing. This also help to better forecast the staffing needs, schedules maintenance and perform lean

Related Documents

Cvs caremark supply chain analysis essay.

CVS Caremark– Supply Chain Analysis Supply chain is the flow of inputs into the company and flow of output out of the company to the customers. This involves suppliers, vendors, contractors, the principal business or producer, distributors, wholesalers, retailers and customers. Therefore, supply chain management has connection with other parts of the business from procurement of supplies to design to production then to sales and administration. It is an integral part of the business. Supply chain management strategies affect every part of the supply chain.…

Riordan Manufacturing Case Study

To meet customer demand, Riordan’s [pic]supply chain process must concentrate on inventory management process in the system to fulfill the orders requested (Chase, Jacobs and Aquilano, 2006,). Riordan currently tracks its inventory manually at many points in the supply chain. With the implementation of an integrated inventory management system Riordan would be able to improve cash flow, inventory visibility, and decision-making as well as manage all the resources utilized to meet customer demand for its…

Lockheed Martin's F-35 Production Line

The introduction and implementation of a Just-In-Time (JIT) approach to this production line would be ideal to reduce lead time, minimize inventory on floor and optimize storage area. In particular, adopting a Kanban (card) system would establish lean manufacturing principles that would help streamline the entire process. There is a current card system that is used throughout the production line to monitor the work and parts applied to the aircraft. However, it is difficult in this production system to achieve true JIT goals due to the dynamics of the supply chain. Because of the large complexity of parts needed to construct the F-35, outside vendors are necessary in order to alleviate the weight of having to produce parts in-house.…

Did Boeing Build The 727

Boeing has designed and manufactured various cargo aircrafts throughout the years to attain the requirements necessitated by industrial freight and cargo operators; this is vital, as the demand for cohesive freight solutions is increasing – the world freighter demand is expected to double by the year 2035. Presented with competition in the 1960’s from aeroplanes such as de Havilland Trident, Sud Aviation Caravelle and British Aircraft Corp. BAC 1-11 and companies like Lockheed, Convair and Douglas, Boeing designed the 727 aircraft, including variants such as a convertible passenger-cargo model; despite challenges such as consumer demand clashes, the 727 was the first commercial airplane to attain the 1000-sales milestone – putting the company…

Boeing Merger

Boeing is a world renown producer of jets and commercial airliners. Boeing is a corporation that also produces things for the United States Military. When Boeing was in the making, William E. Boeing there founder graduated from Yale and wanted to take some risks. He took a risk in the Northwest timber industry which that experience helped him drastically in aviation. Boeing became what it is today under his guidance and in 1934 there was a mandated dispersion of the company.…

Why Is Alaska Airlines Best Known For Their High Levels Of Process Control System

Airlines can examine its supply chain management process. Good management of the company’s suppliers will have a positive impact on the company’s operations because it will assure the company is providing good quality products to their customers, increase the company reputation, reduce operating cost and consequently increase profitability. Furthermore, a good supply chain management can be a competitive advantage for the company because it creates a better relationship with suppliers and enhance the business…

Dreamliner Outline

I would like to start my part of presentation from brief overview of Boeing 787 Dreamliner. Dreamliner as you may already know that nowadays it is well-known jet airliner around the world and It is made by the USA Boeing Commercial Airplanes. It is Boeing's most fuel-efficient airplane and is a unique airliner with the use of composite materials as the fundamental material in the construction of its airframe. According to some experts from Commercial Airplanes, the Boeing 787 Dreamliner's distinguishing features include mostly electrical flight systems, swept wingtips, and noise-reducing chevrons on its engine nacelles. By the way, total revenue in 2015 was $96 billion.…

Boeing Research Paper

One of the most famous aviation companies in the world, Boeing has a long and storied history which few other businesses can equal. The first origins of Boeing came in 1910, when William E. Boeing bought the first airplane factory for his eventual company, The Boeing Company. In 1917, the company helped develop aircraft for World War I. From the 1920s to the 1930s, the company successfully sold numerous aircraft designs to the U.S. Military, which is still does to this day. Prior to and during World War II, the company continued to design multiple aircraft for commercial and military purposes. In 1958, Boeing designed and released its first version of its now-famous airplane line, the Boeing 707.…

International Business Strategy Case Study The Bombardier

Through research, it shows one of the factors that were pointed out as the greatest threat is the uprising cost of doing business. Without a plan that could reduce model cost, it will be difficult for the Bombardier to sustain its low price. These are just a few areas that the Bombardiers must examine to stay competitive in the growing market. Throughout the report there were few essential elements of the bombardier company which should be taking into consideration. At last, the bombardier company must strengthen its development and research department to enhance their future and equip itself to transact with the dynamic…

Dynamics Of Aircraft Degradation Case Study

Assumptions are that the through maintenance the airplane can surpass its intended lifespan, but costs are high. Manufacturers sent 20 years as the replacement age for many models, although it was extended. Analysis made on US commercial airplanes shows that in 1997, 46% were over 17 years and 28% over 20years, whilst in 2001, 31% were over 15years of age and of them 66% of them accounted for the total per block hour maintenance. Nevertheless, degeneration occurs, it is polished by numerous factors; intensity use; quality and quantity of repair; environment; and scheduled maintenance. A point should be taken that roughly 60% of maintenance is…

The Implementation Of The Army Containment System

Due to implementation of the supply ordering process through use of computer-based systems, there has been exponentially decreased amounts of time required to process and receive our everyday sustainment needs such as; parts, food, equipment, and even the personnel required to complete the mission. This improvement has taken time to come to fruition though. There has been a true learning curve over the years that has caused more inefficiencies throughout the services, but as we increase the quality and quantity of training on how to use these systems, we have learned to become much more organized in the ways we do…

Case Study Mattel Corporate Social Responsibility

Corporate Social Responsibility: As a leader in the toy industry, Mattel failed to fulfill its corporate social responsibility and meet the legitimate concerns of society. In the business world, corporations should be responsible for all of stakeholders, including the shareholders, customers, and the society. Thus, the best social responsibility is to create shared value for society and the business (Hitt, Black, and Porter 51).…

Boeing Business Strategy Analysis

It is studying the competitive market, such as Airbus, and working on the continuous development of the company by raising the level of the company's technical, service and management to be able to compete strongly. They worked on the development of some aircraft such as: The 777-300ER comes as a product of Boeing's continuous development. Travelers are also expected to perform well, prompting Boeing to continue to develop and remain the best among its competitors. Since it was introduction, Boeing has improved its 777-300R aircraft by providing state-of-the-art technology, which has added approximately 630 nautical miles (1,166 km), reduced airframe maintenance costs by 14 per cent, On aircraft software to enhance its efficiency. The improved maintenance program increases the time between maintenance tasks, providing about 400 hours per aircraft per year - equivalent to an extra day of paid services per year for each Boeing 777 aircraft, which clearly contributes to increased operational efficiency.…

Boeing Risk Management Case Study

Boeing is an Amercian multinational cooperation that offers aircraft and product support services (Boeing: The Boeing company, no date). Being in the aircraft business involves a lot of risk unless someone is not careful and decisions are not made through careful and accurate analysis. They need to be on top of their game at all times ensuring safety of passengers and to uphold a good reputation to be able to be successful in the industry, in the long run. Risk comes in a number of different ways and are often unexpected. Risk management is fundamental to all business activities.…

Case Study On Supply Chain Management At Haus Mart

By coordinating and streamlining exceedingly critical business forms with Supply Chain Execution, logistics administration suppliers make new chances to: • It manages and moves products more efficiently. Secures and organizes shipments better via computerizing stock management, and incorporating logistics forms with enterprise asset planning system and solutions used by clients and…

Related Topics

  • Southwest Airlines
  • Low-cost carrier

Ready To Get Started?

  • Create Flashcards
  • Mobile apps
  •   Facebook
  •   Twitter
  • Cookie Settings

IMAGES

  1. Case Study Of Boeing Dreamliner

    boeing 787 dreamliner case study summary

  2. Boeing 787 Dreamliner Case Study Pdf

    boeing 787 dreamliner case study summary

  3. Material utilization in the Boeing 787 Dream Liner manufactured by HdH

    boeing 787 dreamliner case study summary

  4. Lessons From Boeing's Dreamliner Supply Chain Missteps

    boeing 787 dreamliner case study summary

  5. Boeing 787 case study answers. Boeing 787: The Dreamliner Case Solution

    boeing 787 dreamliner case study summary

  6. Boeing on the Dreamliner 787: A Case Study

    boeing 787 dreamliner case study summary

VIDEO

  1. Boeing 787-10 Dreamliner

  2. PURE Boeing 787 Dreamliner POWER!✈ What a Sound! B787-8, B787-9 & B787-10

  3. New Lufthansa 787 in business class: a Dreamliner with problems

  4. WSJ: Boeing moving all 787 Dreamliner production from Everett to South Carolina

  5. 787 Dreamliner first flight

  6. ✈Boeing 787-8 DREAMLINER ✈All Nippon Airways [ANA] landing at Düsseldorf International Airport

COMMENTS

  1. Boeing 787

    Boeing 787: The Dreamliner The Boeing Corporation The Boeing Company, founded in 1916, operated three major groups of businesses with a total of six subsidiaries: commercial integrated defense systems subsidiaries including aircraft weapon systems, network systems, support systems, and launch and orbital and the Boeing Capital Corporation.

  2. Boeing 787: Manufacturing a Dream

    This case traces the design and development of the Boeing 787 Dreamliner. Emphasis is on executive leadership and firm strategy in coordinating across a global network of partners in the production of a new aircraft. ... Harvard Business School Case 615-048, February 2015. (Revised May 2015.) Educators;

  3. Crisis in Boeing 787 Dreamliner: An Investigation from Project

    innovative plan of setting up an unconventional supply chain in the aircraft manufacturing. industry in order to develop and produce the Dreamliner. The proposed plan was supposed to. minimize ...

  4. Case study: Boeing's Dreamliner

    The story: When Boeing delivered its new Dreamliner 787 to All Nippon Airlines last month, it was the culmination of a long and drawn-out process. The first delivery came more than three years ...

  5. PDF Boeing 787: The Dreamliner (B)

    Boeing 787: The Dreamliner (B) In April 2008, Boeing confirmed a delay in the 787‐airplane and announced a 14‐month delay in delivering Boeing's most anticipated airplane. The Boeing 787‐airplane, to be put in service in 2008 initially, has become Boeing's

  6. Boeing and the 787 Dreamliner

    Summary. Boeing's development of the 787 Dreamliner provides an excellent case study in decision-making that spans the continuum from the executive suite to the operational levels within Boeing, its outsourced partners, and to the factory floor. The Dreamliner represents a major investment by Boeing in introducing not only new technologies and ...

  7. The Boeing 787 Dreamliner

    The Boeing 787 Dreamliner - a Case Study in Large-Scale Design Integration. D. L. McMullin, A. R. Jacobsen, ... The Boeing Company Seattle, Washington. View all articles by this author. ... The Grounding of the 787 Dreamliner. Show details Hide details. Andres Carrillo. SAGE Business Cases. 2013. SAGE Knowledge.

  8. Case 39: Boeing 787 Dreamliner Project

    It connects the world with 150 plus new nonstop. The Boeing 787 have celebrated one million 787 Dreamliner passenger flights. The project offers the fastest for any twin aisle. It holds the record of 2.5 billion miles flown and 18 billion pounds of oil saved. Currently over 80 customers have ordered more than 1400 787 s.

  9. A Case Study. The Boeing 787 Dreamliner Programme: Leveraging the

    The case study concerns the Boeing 787 Dreamliner programme, beginning in 2009 with the B787-8's first model and continuing to track its evolution until more recent times through the B787-9 and B787-10 models. The commercial aircraft industry is an appropriate research setting for several reasons.

  10. Boeing 787: The Dreamliner

    Boeing dominated the commercial airline manufacturing business since bringing out the first commercial airline jet airliner. But in 2005, it delivered fewer new planes than its fast-moving competitor, Airbus. Boeing responded by transforming its manufacturing business and introducing the first "all-composite" commercial airplane: the 787 (the Dreamliner). In addition to being a revolutionary ...

  11. Ten years on, is the Boeing 787 Dreamliner still more dream than ...

    Once in a generation, a game-changing airplane like the Boeing 787 dreamliner comes along. Its high-tech features set a new benchmark in aviation, but with $32 billion spent on the program so far ...

  12. "Boeing Dreamliner:A Project Management Study" by Fahad Aldhaban, Chris

    The 787 Dreamliner aircraft project required not only the application and integration of new construction materials, it also required new project management techniques for Boeing. By outsourcing most of the aircraft fabrication, Boeing's primary role changed from designer and manufacturer to system integrator. Hindsight shows that more preparation and planning was needed for this transition ...

  13. Boeing and the 787 Dreamliner

    <P>Boeing's development of the 787 Dreamliner provides an excellent case study in decision-making that spans the continuum from the executive suite to the operational levels within Boeing, its outsourced partners, and to the factory floor. The Dreamliner represents a major investment by Boeing in introducing not only new technologies and management processes, but also developing more efficient ...

  14. History of Boeing 787 Dreamliner, the Plane That Started a Revolution

    Mar 1, 2020, 5:00 AM PST. Boeing 787 Dreamliner. AP. First flown in 2009, the Boeing 787 was the first next-generation plane produced by a major aircraft manufacturer. The jet was produced ...

  15. Boeing 787 Dreamliner: Innovation Gone Wrong?|Operations|Case Study

    The case is about the 787 Dreamliner, an airplane developed by the US based airplane manufacturer, Boeing Airplane Company (Boeing). The case examines the reasons that prompted Boeing to initiate the 787 project. It highlights the making of the aircraft, which was expected to change the dynamics of the world aviation industry. The case also highlights the distinguishing features of the ...

  16. Boeing 787: The Dreamliner Harvard Case Solution & Analysis

    Boeing dominate commercial enterprises for the production of airlines, as revealing the first commercial airliner. But in 2005, she placed fewer new planes than its fast-moving rival, Airbus. Boeing responded by turning its manufacture and implementation of business first "all-composite" commercial aircraft: 787 (Dreamliner).

  17. Data-driven reliability analysis of Boeing 787 Dreamliner

    Boeing's commercial aircraft business has been in service for nearly 100 years, and its current fleet includes the 737, 747, 767, 777, and 787 families. 1 The Boeing 787 Dreamliner was introduced to the market in 2011 as a mid-size, dual-aisle, wide-body aircraft. Boeing marketed the 787 as a revolutionary aircraft, with an array of new ...

  18. Boeing 787 Dreamliner

    case study boeing 787 dreamliner stakeholder needs and requirements design process and concurrent engineering boeing 787 dreamliner video: cnn, sept 2011. Skip to document. ... Summary - carl 2. Design and Innovation Fundamentals. Summaries. 96% (25) 10. B1 Assignment Report . Design and Innovation Fundamentals. Assignments. 100% (9)

  19. The Boeing 787 Dreamliner

    The development of an all-new commercial transport airplane presents a unique opportunity for the practical application of human factors and ergonomics skills and methods in a large-scale engineeri...

  20. The Boeing 787 Dreamliner

    An optimization approach for team coordination through information sharing. Conference Paper. Aug 2017. Yijie Peng. Edward Huang. Jie Xu. Chun-Hung Chen. Request PDF | The Boeing 787 Dreamliner ...

  21. Boeing 787 Dreamliner case study.docx

    Executive Summary Airbus took over the market leadership, and this resulted in Boeing to improve themselves and acquire an advantage over Airbus and other competitors. Boeing decided to improve their product and service so that it could match with the customers' expectations instead of merely just reducing the plane ticket price. This led to the introduction of the Dreamliner Boeing 787 ...

  22. Boeing 787: The Dreamliner

    But in 2005, it delivered fewer new planes than its fast-moving competitor, Airbus. Boeing responded by transforming its manufacturing business and introducing the first "all-composite" commercial airplane: the 787 (the Dreamliner). In addition to being a revolutionary new commercial airliner, the 787 attempts to change the large "spoke-and ...

  23. Boeing 787 Dreamliner: Case Study

    Introduction Boeing 787 Dreamliner is the project plan of Boeing company about light weight aircraft with high technology. The project of this aircraft has facing several problems such as software problem that led to engine shutting down automatically, lithium ion battery that causes fire inside the aircraft and others problem that led delay in the production.